Every addition starts with zoning, not design. Your municipality sets limits on how close you can build to each property line, how much of the lot can be covered, and how tall the house can be. Those rules decide whether you are building out the back, out the side, or up, so check them before falling in love with a floor plan.
If the addition you want does not fit the by-law, you can apply for a minor variance through the local Committee of Adjustment. It is a normal process, but it adds time, so it belongs at the start of the schedule rather than in the middle.
With zoning settled, drawings are prepared and submitted for a building permit. The permit review looks at structure, insulation, exits, and how the new work connects to the existing house. Construction starts only after the permit is issued, and inspections follow at set stages such as footings, framing, and insulation.
On site, the sequence is predictable: excavation and foundation, framing, roof and windows to make the shell weather-tight, mechanical rough-ins, insulation, drywall, and finishes. The opening into the existing house is usually cut late, so your home stays closed and comfortable for most of the build.